Saransk Milk Factory, Russia
Yalutorovsk Milk Factory, Russia
Danone is the world's leading food and drink company, operating in more than 120 countries.
GRYS Power in partnership with Danone implemented two wastewater treatment plants at sites in Saransk and in Yalutorovsk. Both projects were implemented as B.O.O.T. projects (Build-Own-Operate-Transfer), including design, construction, commissioning, operation and maintenance for 10+ years. Operation and maintenance are carried out by GRYS Power’s team.
OBJECTIVES
- Build wastewater treatment plants under harsh environmental conditions within the shortest possible time
- Provide plant management and operation services
- Ensure guaranteed service performance and service availability
- Provide additional revenue to the client
PACKAGE OF SERVICES
- Service contract for design, construction, operation and maintenance of WWTP
- Modular Solution: fully transportable solution for outdoor installations, adapted to environmental conditions
IMPLEMENTED SOLUTIONS AND RESULTS
GRYS Power provided technical solutions which resulted in high operational performance of facilities, as a result of its extensive experience as a company which operates and maintains this kind of systems, with ensuring high efficiency of the WWTP systems for both factories in the long term, without capital investment and risks for the client.
Saransk Milk Factory OJSC
- Date of signing: January 2014
- Term: 10 years
- Commissioned: July 2015
- Installation and commissioning completed within 11 months
- Volume of treated wastewater: 1,300 m3/d
- Max amount of treated Chemical Oxygen Demand (COD): 4,303 kg/d
Yalutorovsky Milk Factory OJSC
- Date of signing: April 2014
- Term: 10 years
- Commissioned: January 2016
- Installation and commissioning completed within 6 months
- Volume of treated wastewater: 2,600 m3/d
- Maximum amount of treated Chemical Oxygen Demand (COD): 10,000 kg/d